Informational Update December 2, 2020
Green text signifies updates.
Blue text signifies those items previously announced but ongoing.
18th Avenue – Cherry Hill Medical Pavilion
- Sabey Construction is working with Seattle City Light to terminate power to the 3 structures. This work is expected to be complete by mid-December.
- Landscaping removal will continue the week of December 7, followed by soil excavation.
- In mid-December, demolition of all 3 structures will begin and should conclude before the end of December.
- Soil grading will occur in December and into January.
City’s Notice to Community Process
- Seattle Department of Construction & Inspections (SDCI) sends out notifications to adjacent property owners and tenants within a 300-foot radius.
- Project information is posted on the Land Use Information Bulletin Section of the SDCI website
- Anyone providing comments to SDCI during the MUP process and requests to be on the notification mailing list OR if anyone signing up at the Early Design Guidance/Design Review Board meetings will receive notification from the City.