Informational Update December 2, 2020

Green text signifies updates.
Blue text signifies those items previously announced but ongoing.

18th Avenue – Cherry Hill Medical Pavilion

  • Sabey Construction is working with Seattle City Light to terminate power to the 3 structures.  This work is expected to be complete by mid-December.
  • Landscaping removal will continue the week of December 7, followed by soil excavation.
  • In mid-December, demolition of all 3 structures will begin and should conclude before the end of December.
  • Soil grading will occur in December and into January.

City’s Notice to Community Process

  • Seattle Department of Construction & Inspections (SDCI) sends out notifications to adjacent property owners and tenants within a 300-foot radius.
  • Project information is posted on the Land Use Information Bulletin Section of the SDCI website
  • Anyone providing comments to SDCI during the MUP process and requests to be on the notification mailing list OR if anyone signing up at the Early Design Guidance/Design Review Board meetings will receive notification from the City.